What is the delivery time for a rebar machine from China?
Quick answer: production is 7–25 days for standard machines, plus 15–35 days sea freight depending on the destination.
Typical lead times:
- GQ50A cutter — 7–15 days build
- CNC benders and stirrup machines — 15–25 days build
- GDLWZX-32 bending center — 25–40 days build
Then add sea transit: roughly 15–20 days to Africa's east coast, 7–12 days to Southeast Asia, 20–35 days to West Africa and the Middle East.
How to buy: if you have a deadline, tell us the date you need the machine on site; we work backward and confirm a committed shipment date.
Message us on WhatsApp with your deadline for a firm delivery schedule.
Machines in these answers
GQ50A
Rebar Cutting Machine
Rebar cutting machine for 6-50 mm round and 6-36 mm ribbed bars, built for daily site and shop use.
| Bar diameter cut | A3 round bar / 6-50mm |
|---|---|
| Rebar grade II (deformed) | 6-40mm |
| Rebar grade III (deformed) | 36mm |
| Moving blade strokes | 26/min |
| Moving blade stroke | 40mm |